State Route 77 Blasting Project To Continue Through End Of April

A safety project to remove overhanging rock along State Route 77 between Globe and Winkelman east of the Phoenix area will require an additional month of daytime restrictions, according to the Arizona Department of Transportation.

Because of the difficult terrain crews have encountered blasting and removing debris, full closures between 10 a.m. and 3 p.m. Mondays through Thursdays are now scheduled to continue through the end of April.

Between 7 a.m. and 10 a.m. and 3 p.m. and 5 p.m. Mondays through Thursdays, traffic will alternate in one lane. Expect 15-minute delays during those hours.

The work between mileposts 150 and 161 in the Dripping Springs area is reducing the chances of rocks falling from cliffs onto the highway.